Ramesh Kumar Jain v. State of U.P. and 5 Others
Case brief
What is this about?
The High Court disposed of a writ petition seeking a mandamus to direct the Executive Engineer to grant a new electricity connection. Relying on the U.P. Supply Code, 2005, the court ordered the respondent to consider the application and pass a reasoned order within four weeks.
What did the court decide?
Direction to respondent no. 3 to consider the petitioner's application for new electricity connection and pass a reasoned order within four weeks.