Istiyaque v. State of U.P. and 2 Others
Case brief
What is this about?
Petition sought compensation for land used by respondent no. 2 for an electricity transformer. Court directed petitioner to submit a representation to the District Magistrate under the Electricity Act, 2003 and Works of Licensees Rules, 2006 for consideration within specified timelines.
What did the court decide?
Direction to petitioner to submit representation to District Magistrate for consideration under Electricity Act, 2003; Magistrate to decide within one month.