Ms Crystal Infrastructure v. Uttarakhand Rural Roads Development Agency
Case brief
What is this about?
Uttarakhand HC (DB, 04.05.2026, Manoj Kumar Gupta CJ & Subhash Upadhyay J) dismisses Writ Petition (M/B) 337 of 2026 by MS Crystal Infrastructure v. Uttarakhand Rural Roads Development Agency: challenge to Tender Evaluation Committee order dated 24.04.2026 recommending re-tendering after single responsive bid in technical evaluation under E-procurement notice 28.01.2026 (Gram Sarak Yojna works). Key points: single responsive bid mandates re-tendering per prescribed guidelines; rejection of respondent no.3's bid for want of original documents (para 5 NIT12(P-IV) 202526; Standard Bidding Documents S.1 Cl.6.2, S.2 Cl.12.2(d)) not challenged by that bidder; NRRDA circular 25.01.2026 on scanned copies insufficient to upset decision; petitioner free to bid afresh; no interference warranted.
What did the court decide?
Where only a single bid is found responsive, re-tendering has to be done as per the prescribed guidelines; the respondents took the re-tendering decision as per the prescribed norms, the rejected bidder (respondent no. 3) did not challenge his rejection, and the petitioner retains the opportunity to participate in the fresh tender process.