Smt. K. Geeta Krishna v. The State of Telangana
Case brief
What is this about?
Electricity connection; release of power supply; refusal for non-production of occupancy certificate; TGSPDCL/TSSPDCL; GHMC Serilingampally Circle; Article 226 mandamus; Articles 14 and 21; Gachibowli Village, Serilingampally Mandal, Rangareddy District; disposal at admission stage in terms of W.P. No. 4292 of 2025 (order dated 14.02.2025); direction to consider connection request on compliance with terms and conditions; decision within one week; no costs; I.A. No. 1 of 2025 under Section 151 CPC closed.
What did the court decide?
Writ petition disposed of at the admission stage directing Respondents 2 to 5 to consider the petitioner's request to provide electricity connection supply to her plot bearing No. 97 part in Sy. No. 92/L, 92/3 to 92/18, Gachibowli Village, upon compliance with the required terms and conditions as per the rules in force, and to take a decision in accordance with law within one week from receipt of a copy of the order; no order as to costs; pending miscellaneous applications closed.