N. Sreevani v. The State of Telangana
Case brief
What is this about?
Refusal of construction permission by Greater Warangal Municipal Corporation via rejection memo dated 30.01.2016 (Roc.No.G1/38532/2015) allegedly antedated and served 29.04.2016 after LRS expiry (01.03.2016); writ allowed; respondent directed to consider application without insisting on LRS following KUDA regularization dated 28.04.2018. Keywords: writ of mandamus; Article 226; HMC Act stipulated period; Layout Regularization Scheme (LRS); antedated memo; deemed permission; adjacent-owner parity (Bairi Yadava Reddy, Permit No.98); Jagruti Colony demarcation; Telangana HC W.P. No.17769/2016.
What did the court decide?
Writ petition allowed; respondent No.2 (Greater Warangal Municipal Corporation) directed to consider the petitioner's application for construction permission without insisting for LRS and to pass orders within four (04) weeks from receipt of a copy of the order; no order as to costs; miscellaneous petitions pending, if any, stand closed.