Gabbeta Rajender Rao v. The State of Telangana
Case brief
What is this about?
The High Court disposed of a writ petition filed by petitioners claiming delay in survey and demarcation of their agricultural land. The Court directed the Tahsildar and Surveyor to complete the survey within 45 days.
What did the court decide?
Respondents directed to complete survey and demarcation of lands within forty-five days.
What the court decided
[3183 ]
HIGH COURT FORTHE STATE OF TELANGANA AT HYDERABAD (Special Original Jurisdiction)
FRIDAY, THE SIXTEENTHDAYOF FEBRUARY TWO THOUSANDAND TWENTYFOUR
PRESENT
THE HONOURABLESRIJUSTICE B.VIJAYSEN REDDY
WRIT PETITION NO: 4018 OF 2024
Between:
- -- i.-6rno.t" Rajender Rao, S/o: Sadashiva ngg,. uggd^,999-'l i.g--,I""t' Occ. Agriculture,R/o KatkurVillage, Akkannapet Mandal'srgdrPgl lrlsin:)^ ^-^
- z. Smt. G"abbeta Swapna,W/o: Gabbeta RajenderRao' aged aoout 3u Years' ' 5;. isl"ic-Jtu*, Rv6 ritkur vittage, Akkanhapet Mandal' t'o13e;P,rt3tnl=*t
AND
- 1 The State of Telangana,Rep.by its Principal Secretary Revenue Department Secretariat,HYderabad
Issues for consideration
1 issue framed by the court
Whether the writ petition should be disposed of directing the respondents to complete the survey and demarcation of the petitioner's agricultural land within a specified period.
Parties & counsel
- petitioner
Rajender Rao
- petitioner
Gabbeta Swapna
- respondent
The State of Telangana
Coram
Case details
As recorded by the court registry
- Court
- Telangana HC
- Decided on
- · February
- Registered
- Case no.
- WP/4018/2024
Similar cases