The Indian Flume Pipe Co. Ltd. v. The State of Telangana
Case brief
What is this about?
This court disposed of a writ petition and a civil petition filed by a company seeking release of contractual dues and interest. Although the government submitter stated the entire amount was paid, the court directed a specific respondent to consider the petitioner's representation regarding interest on delayed payments within one month.
What did the court decide?
Instrumentality of the court did not dispose to allow or dismiss, but directed the Superintending Engineer to consider the petitioner's representation dated 02.07.2022 regarding the contractual intere