M/s Swarna Techno Constructions Pvt. Ltd. v. the Union of India
Case brief
What is this about?
This court held that the dispute in the writ petition involved purely contractual issues and disputed questions of fact, making it unsuitable for judicial review under Article 226. Nevertheless, the court disposed of the petition by directing the respondents to consider the petitioner's representation and pass appropriate orders within six weeks.
What did the court decide?
The writ petition was disposed of by directing Respondent No.3 to consider the petitioner's representation dated 13.09.2022 and pass appropriate orders within six weeks from the date of receipt of a c