M/S Salient Projects Private Limited, Hyd v. M/S R.K. Electric Automation Limited, Hyd
Case brief
What is this about?
The court allowed joint arbitration applications filed by the applicant against the respondent. Based on the arbitration clause in Supply and Erection Agreements and the respondent's failure to file a counter affidavit or reply to notices, the court appointed Mr. B.P. Jeevan Reddy as the sole arbitrator to resolve seven disputes arising from the contracts.
What did the court decide?
Appointment of Hon'ble Sri Justice B.P.Jeevan Reddy as the sole Arbitrator for resolution of disputes arising out of multiple agreements between the parties.