M/S. Aditya Construction Co. India Ltd. v. The Southern Power Distribution Company of Telangana State Ltd.
Case brief
What is this about?
The High Court directed respondents to release power supply to the petitioner's premises, subject to compliance of terms and conditions and furnishing an undertaking to obtain an occupancy certificate within three months. Failure to produce the certificate allows respondents to take appropriate legal action.
What did the court decide?
Directions to release power supply subject to terms and compliance, to furnish an undertaking to obtain an occupancy certificate within three months.