Essar Power M.P. Limited, v. Southern Power Distribution Company of Andhra Pradesh
Case brief
What is this about?
The court held that a respondent cannot unilaterally compel a bidder to extend bid validity or bank guarantee absent mutual agreement. Since the petitioner withdrew the petition and was not selected, the respondent was directed to return the security.
What did the court decide?
Leave granted to withdraw petition; Respondent directed not to invoke bank guarantee and to return it within two weeks.