The Project Officer, Itda, for ( Ptg-Chenchu), v. R. Lingamaiah
Case brief
What is this about?
The High Court set aside the Industrial Tribunal's order granting reinstatement to workmen terminated by ITDA. Relying on Bharat Sanchar Nigam Ltd., the Court held that where temporary workers on non-sanctioned posts are terminated due to lack of work/funds, compensation is the proper remedy, not reinstatement, despite violation of Section 25-F.
What did the court decide?
Orders of reinstatement set aside; each claimant awarded Rs. 10,000 compensation as lump sum.