M/s Khabri Exports, v. a.P.Central Power Distribution Company Ltd. (Apcpdcl)
Case brief
What is this about?
The High Court of Andhra Pradesh held that the petitioner was liable to pay minimum electricity charges for two years from the supply commencement based on the 120 KVA revised sanction. However, any claim for further periods was barred under Section 56(2) of the A.P. Electricity Act, and the petitioner was entitled to credit for payments already made.
What did the court decide?
The petitioner is liable to pay minimum charges for CMD of 120 KVA for the period of two years from June 2007 to May 2009. Claims for further periods are barred by Section 56(2). Amounts already paid