M/s. Anand Construction Company, v. The General Manager
Case brief
What is this about?
High Court held that a writ petition for payment of final bill and security deposit in a construction contract is not maintainable under Article 226 as it requires adjudication of financial disputes. Petitioner directed to approach railway for fresh representation.
What did the court decide?
Petitioner permitted to approach the third respondent for receiving payments by making a fresh representation; admitted amount to be released within four weeks.