Pappla Dali Naidu, v. Land Acquisition Officer --Cum-- Revenue Divisional Officer.
Case brief
What is this about?
A writ petition was filed regarding the non-mandatory reference of the land acquisition award to the civil court. This court held that the respondent's delay in acting on the petitioners' application for a reference constituted sufficient ground for interference.
What did the court decide?
Directing the respondent to make a reference to the civil court, if not already made, within a period of three months from the date of receipt of a copy of this order.