M/s.Sai Ganapathi Sc and Bc Labour Contract Co.op. v. The Executive Engineer, Roads and Buildings (Randb) Division
Case brief
What is this about?
A writ petition filed by a society entrusted with constructing a record room. Respondents withheld payment due to lack of Letter of Consent despite work completion. Court held petition maintainable against administrative inaction and directed payment within four weeks.
What did the court decide?
Directions to respondents to complete formalities and pay Rs. 3,00,000/- with interest within four weeks from the date of receipt of the order.