What is this about?
Civil Appeal challenging an execution order by NCDRC. The Supreme Court examined whether the appellant was entitled to construction escalation costs until 15.10.1998 or 30.04.1997. The Court held that the review order only substituted one date in the context of ground rent, leaving the escalation date unchanged.
What did the court decide?
Civil Appeal dismissed with an observation to the effect that the construction cost of escalation remains payable only till 30.04.1997 as per the order of 07.07.2008.