The Electricity Department, Rep. by Its Superintending Engineer, Port Blair and Anr. v. Mis Suryachakra Power Corporation Limited
Case brief
What is this about?
Electricity Department Port Blair v. Suryachakra Power Corporation Ltd.; suo moto allowance of additional IDC, FC and IEDC by Appellate Tribunal for Electricity set aside; delay in achieving commercial operation; deemed generation charges versus additional IDC/FC/IEDC; five member committee report final project cost Rs. 70.61 crores accepted by Administration; CEA funds tied up basis Rs. 77.595 crores; JERC completed cost allegedly contrary to PPA; no substantial question of law; Civil Appeal No. 1652 of 2015; [2016] 9 SCR 68.
What did the court decide?
Appeal allowed only to the limited extent that the Appellate Tribunal's judgment is set aside insofar as it allowed a suo moto increase in IDC, FC and IEDC for the delay in execution of the project; on other points the appeal is dismissed; appeal disposed of with no costs. ¶71