Executive Engineer, Uttaranchal Power Corporation v. M/S. Kashi Vishwanath Steel Ltd. & Ors.
Case brief
What is this about?
promissory estoppel; doctrine of promissory estoppel; electricity tariff; 15% surcharge; independent feeder; 400/220/132 KV sub-station; assured supply 500 hours per month; rebate 1% per 10 hours shortfall; Tariff Rate Schedule HV-2; U.P. Electricity Regulatory Commission Notification 07.08.2000; circular 08.09.2000; exemption office memo 24.10.2000; Uttaranchal/Uttarakhand Power Corporation; successor-in-interest liability; bifurcation of U.P. Power Corporation; Section 63 U.P. Reorganisation Act; withdrawal of exemption; revised electricity bill; Writ Petition No. 936 of 2001; High Court of Uttaranchal Nainital; mandamus; recall of judgment dated 13.12.2007; costs Rs. 50,000
What did the court decide?
Appeal allowed; order dated 17th January, 2007 of the High Court of Uttaranchal in Writ Petition No.936 of 2001 set aside; costs of Rs.50,000/- imposed.