M/S Unissi (India) Pvt. Ltd. v. Post Graduate Institute of Medical Education & Research
Case brief
What is this about?
Validity of arbitration agreement absent buyer's signature: tender acceptance plus conduct (supply, acknowledgement on delivery challans, letters referencing tender enquiry, use of goods for a year) satisfies Section 7, Arbitration and Conciliation Act 1996; Section 11(4)(a) application dismissed by Additional District Judge, Chandigarh set aside by Supreme Court; Chief Justice of High Court of Chandigarh (as printed) directed to appoint Arbitrator; relied on Smita Conductors (2001) 7 SCC 728 and Nimet Resources (2000) 7 SCC 497; referred SBP & Co. v. Patel Engineering (2005) 8 SCC 618; Article 136 maintainability left open; unpaid goods Rs.22,16,853.60; bank guarantee/earnest money encashed and forfeited.
What did the court decide?
Impugned order of the Additional District Judge, Chandigarh set aside; appeal allowed; matter directed to be placed before the Hon'ble Chief Justice of the High Court of Chandigarh to appoint an Arbitrator in accordance with law to resolve the dispute between the parties; no order as to costs.