A to Saxena asking the latter to issue orders to his contractors to mend and rectify all the cuttings and damages properly so that the. building may be in a fit condition for h3nding over on August 1,. 1955. A copy of this letter was forwarded to M/s Patna Flooring Company for their inforation and necessary action, and they - were asked to rectify all the defects pointed out to them and to B complete the remaining work by the scheduled date. It may be not'ced that Saxena's contract in its entirety was not tenninated : only a part of the contract had been taken away from him. Direc-tions had therefore to be given to him to cJmplete the contract of the building and to hand over the same by July 31, 1955, and_ to M/s Patna Flooring Company to rectify all the defects pointed. C out of them. If M/ s Patna Flooring Company were merely a subcontractor, there is no reason why a copy of this letter should have. been addressed to them and that they should have been asked to rectify the defects. On July 21, 1955 a statement of account was drawn up in respect of the mosaic work done by D Ml s Patna Floming Company in the Rajnd1 a Surgical B1ock'" It is described as "a statement of account of mosaic work between G. P. Saxena and Messrs Patna Flooring Cvmpany". On the. credit side of the account are three items : Rs. 57,443 / 4/3 in re5pect of bill dated November 2j, 19.)3; Rs. 4,719/9/3 in respect of bill dated March 31, 1955 and Rs. 14,000/- in respect of E bill dated July 13, 1955 through the Sub-Divislonal Officer No. Ill Sub,division, Construction Division, Patna. On the debit side. are various· items of payments aggregating to Rs. 49,754/9/3leaving a balance of Rs. 26,408/ 13/3. Against that amount a cheque for Rs. 15,000/- is recorded as given on July 21, 1955on the Bank of Bihar Ltd., leaving a balance of Rs._ 11,408/13/3 .. F There are two notes at the foot of this account. The first part of note No. (1) deals with the bill dated March 31, 1955 which is not material. It then proceeds to record that M/s Patna Flooring Company will be responsible for rectification of the defects in mosaic work in bill No. BP/1838/35/55 and 93/55 dated July 13, 1955 and March 31, 1955 respectively. Note No. (2) states G that M/ s Patna Flooring Company will reali e from Saxena im- - mediately the amount of the claim for work included in the third bill. Th's is signed by the first respandent. At the foot of these, two notes there are two endorsements one signed by Saxena and the other by the first repondent In the endorsement signed by H Saxena it is stated that the acc0unt was crrect and he admitted that Rs. 11,408/13/3 were due from him which he promised "topay very soon". It was also stated that the terms of the originar agreement between Saxena and M/ s Patna Flooring Company