M/S Parmar Construction Company v. West Central Railway
Case brief
What is this about?
A commercial court dismissed an appeal arising out of an arbitral award concerning defective box girder removal and penalty charges. The High Court held the alleged objections did not fall within Section 34(2) or 34(2A) of the Arbitration Act as they pertained to factual questions.
What did the court decide?
The appeal was dismissed as the objections raised did not fall within the scope of Section 34 of the Arbitration and Conciliation Act.