M/S Sethi Construction Company, v. Power Grid Corporation of India Ltd.
Case brief
What is this about?
Rajasthan HC Jaipur DB CMA 2167/2025 (28.10.2025), Sethi Construction Company v Power Grid Corporation of India Ltd. & Arbitral Tribunal (Shri Sukhjinder Singh, Sole Arbitrator). Keywords: Section 34 Arbitration and Conciliation Act 1996 objections; award dated 29.01.2019 predating Division Bench order dated 05.04.2019; D.B. Special Appeal Writ No.197/2019; Civil Writ Petition No.16258/2018; sole arbitrator nomination and appointment upheld; Sections 8 and 11; Section 16 competence of arbitral tribunal; functus officio no power to amend award; unimplementable order treated as otiose; judicial propriety subordinate court must follow High Court judgments; award declared non est void ab initio set aside; award upheld, no costs; Commercial Court No.2 Jaipur Metro-II.
What did the court decide?
Appeal allowed; the Commercial Court's Section 34 judgment (declaring the award non est and void ab initio) set aside; the Arbitrator's order/award dated 29.01.2019 upheld in law; no order as to costs.