Naolin Infrastructure Pvt.Ltd. v. Firm M/S Kalpana Industries
Case brief
What is this about?
The High Court of Rajasthan dismissed a Section 5 of the Limitation Act application seeking condonation of a 548-day delay in filing a Civil Revision Petition, holding that the petitioners failed to establish sufficient cause for the delay.
What did the court decide?
The application under Section 5 of the Limitation Act was dismissed; consequently, the Civil Revision Petition was also dismissed as being barred by limitation.