Sms Limited v. State of Rajasthan
Case brief
What is this about?
Appellant challenged termination of contract by State authorities for delay in setting up Block Level Water Testing Laboratories. High Court observed that while natural justice applies to State contracts, interference was inappropriate as termination was based on disputed facts of delay impacting project timelines. Appellant directed to approach civil court.
What did the court decide?
Appeal disposed of; Appellant directed to approach civil court for appropriate relief regarding contract termination.