Sumarmal Kataria and Anr. v. Union of India and Ors.
Case brief
What is this about?
The High Court disposed of multiple connected writ petitions concerning land acquisition compensation. Relying on a Co-ordinate Bench decision in Man Singh, the court directed respondents to re-determine compensation for land acquired under the National Highways Act, as awards were passed after the deadline of 31.12.2014, requiring application of the 2013 Act.
What did the court decide?
Directing respondents to re-determine the amount of compensation payable to the petitioners in accordance with the provisions of the Act of 2013 within three months.