Ceylon Fusion Ayurveda Pvt. Ltd. v. Advance India Projects Ltd. & Anr.
Case brief
What is this about?
Ceylon Fusion Ayurveda Private Limited v. Advance India Projects Limited and another; CR-2766-2026 (O&M) and CR-2780-2026 (O&M); High Court of Punjab and Haryana at Chandigarh; Pankaj Jain, J.; consent disposal of revision petitions; arrears of unpaid rent ₹ 27,86,620/- (approx.); instalment payment 50% in 02 weeks and 50% in two months; restoration of amenities; running business from demised premises; rent and CAM charges at current rate; payments subject to final decision of lis; undertaking by counsel; Contempt of Courts Act; decision dated 10.04.2026.
What did the court decide?
By consent: petitioner(s) to pay 50% of the arrears (₹ 27,86,620/- approx., including unpaid rent) within 02 weeks and the remaining 50% within a further two months; respondent(s) to allow petitioner(s) to run their business from the demised premises and restore all amenities forthwith; petitioner(s) to continue paying rent and CAM charges at the current rate; all payments subject to final decision of the lis; breach of commitments actionable under the Contempt of Courts Act.