Sumit Taneja v. State of Punjab and Others
Case brief
What is this about?
CWP-4928-2025 (O&M) | Sumit Taneja v. State of Punjab | High Court of Punjab and Haryana, Chandigarh | decided 27.08.2025 | mining lease, village Pipli, Hadbast No.357, Tehsil Shahkot, District Jalandhar (open auction 05.07.2017) | Dhusi/Dhushi Dam passage over Satluj River stopped (executive order 30.12.2019; HC order 27.01.2020) and restored by order dated 14.10.2020 in CWP-1325-2020 subject to undertaking (Annexure P/10) | undertaking filed 03.12.2020; mining resumed 10.12.2020 under Chief Engineer's orders | exemption/moratorium from mining dues installments for 14.10.2020–12.12.2020 denied by order dated 10.02.2025 of Executive Engineer/District Mining Officer | delay held attributable to petitioner; Covid-19 plea rejected | writ petition dismissed; misc. applications disposed.
What did the court decide?
The petitioner was aware, from this Court's order dated 14.10.2020, that he had to submit the undertaking in the prescribed format (Annexure P/10); there is nothing on record to show any earlier attempt by him to submit it which was not accepted; the undertaking was submitted only on 03.12.2020 and mining resumed within a week thereafter.