Ms Onkar Infrastructure v. the State of Punjab and Others
Case brief
What is this about?
Onkar Infrastructure v. State of Punjab; CWP-4259-2025; High Court of Punjab and Haryana at Chandigarh; Kuldeep Tiwari, J.; decided 26.03.2025; Articles 226/227 Constitution of India; mandamus for release of outstanding payment ₹17,52,790/- with interest @ 12% p.a.; retrofitting Blocks D & E, DAC Patiala, District Treasury Officer/RTA office, provision of 1 lift; representations dated 05.06.2023 and 10.12.2024 (Annexures P-4, P-5); Speaking Order No.398 dated 19.02.2025, Executive Engineer, Electrical Division, PWD B&R Branch, Patiala; admitted amount to be released within ten days; petition not pressed; closed with liberty to pursue statutory remedies; disposed of accordingly.
What did the court decide?
No adjudicated relief; petition closed ('Disposed of accordingly') with liberty reserved to the petitioner to pursue statutory remedy(ies) if the grievance survives, after the State undertook to release the admitted amount within ten days.