M/S Sunil Kumar Contractor v. State of Punjab and Ors.
Case brief
What is this about?
M/s Sunil Kumar Contractor v. The State of Punjab and others; CWP-19780-2025 (O&M); Punjab Mandi Board; Punjab Roads and Bridges Development Board; Executive Engineer (C), Ludhiana; speaking order dated 22.08.2025; Annexure R-2/1; outstanding amount Rs.9,71,226/-; RTGS release on 29.08.2025; claim for interest declined; Justice Suvir Sehgal; writ petition disposed of on 02.09.2025.
What did the court decide?
No further relief adjudicated; writ petition disposed of after respondents No.2 to 4 released the outstanding amount of Rs.9,71,226/- to the petitioner through RTGS on 29.08.2025, with the claim for interest on the said amount declined. ¶¶25