M/S Sunil Kumar Contractor v. State of Punjab and Ors.
Case brief
What is this about?
CWP-18724-2025, High Court of Punjab and Haryana at Chandigarh, decided 25.08.2025 by Suvir Sehgal, J. (Oral): writ petition by M/S Sunil Kumar Contractor against the State of Punjab and others disposed of after State counsel (Siddharth Sandhu, AAG) stated, on instructions of the Executive Engineer, PWD (B&R), Ludhiana, that final payment of Rs.13,15,300/- due to the petitioner from the Punjab Mandi Board (per Memo No.1273 dated 21.08.2025, deciding legal notice dated 14.05.2025) would be released within eight weeks; petitioner's counsel (Ankur Gupta) satisfied.
What did the court decide?
Undertaking by State counsel, accepted by the Court, that the final payment of Rs.13,15,300/- due to the petitioner from the Punjab Mandi Board shall be released within a period of eight weeks; writ petition disposed of. ¶¶10