Pawan Kumar Govt Contractor v. State of Haryana and Others
Case brief
What is this about?
CWP-14315-2025 (O&M); Punjab and Haryana High Court; Pawan Kumar Govt Contractor v. State of Haryana; government contractor pending bills; Public Health Engineering Division No.1 and No.2, Sirsa; speaking order dated 19.06.2025; letter No. 11866 dated 19/06/2025; Rs.23,18,759/-; Rs.45.06 lacs; 139 bills; payment within six months; no interest if timely payment, liberty to claim interest on default; writ petition disposed.
What did the court decide?
Payment of Rs.23,18,759/- (PHED Division No.1, Sirsa) within four months without interest, subject to Treasury/Finance Department clearance and availability of LOC; payment of Rs.45.06 lacs (139 bills) within six months as assured by State counsel; liberty to petitioner to claim interest if the time frame is not adhered to. ¶22