Government of India and Anr. v. Bhajan Lal and Ors.
Case brief
What is this about?
Interest on compensation under National Highways Act 1956 acquisitions runs from date of vesting under Section 3D(2), not from date of award; Section 3H(5) nine per cent interest on arbitrated excess from date of taking possession under Section 3D; Section 3G determination; Section 3A(1), 3D, 3E, 3F, 3H scheme; contrast with Land Acquisition Act 1894 Sections 11, 16, 28 and RFCTLARR Act 2013 Sections 4(2), 26, 30(3), 82 (twelve per cent interest from social impact assessment notification); Article 14 and Article 31A of the Constitution; equality cannot be applied negatively to deny statutory benefits; Golden Iron and Steel Forging 2011(4) RCR (Civil) 375 distinguished on the interest-date question; R.L. Jain v DDA (2004) 4 SCC 79 and SLAO v Karigowda (2010) 5 SCC 708 relied on; Champalal Najlya Pawara 2024(6) BCR 38 and Sri Balappa Bharmappa Gasti, Civil Revision Petition No.100118 of 2018 (19.12.2018) referred; NHAI/Government of India v landowners; execution proceedings on specific award; prospective operation declined; Punjab and Haryana High Court at Chandigarh; Pankaj Jain, J.; CR-289-2021 (O&M) and connected revisions; decided 23.07.2025; reportable, reasoned.