M/S Gagandeep Singh and Associates v. Greater Area Mohali Development Authority through Its Chief Administrator
Case brief
What is this about?
Keywords: Section 11(6) Arbitration and Conciliation Act 1996; appointment of arbitrator; GMADA / Greater Mohali Area Development Authority; Clause 25 General Terms of Contract; disputes resolution mechanism; Engineer's decision within 60 days; Superintending Engineer as sole arbitrator; liquidated damages 1% raised to 5% reduced to 0.25%; notices dated 15.06.2023 and 19.08.2023; hedging and fencing green belts Aerocity SAS Nagar; sole arbitrator Mr. Justice Darshan Singh (former Judge); Fourth Schedule fee; Section 29-A time limit; Section 12 disclosure mandate. Bench: Jagmohan Bansal, J (oral). Decision date: 05.05.2025. Disposition: application allowed; sole arbitrator appointed. No precedent cases cited or relied upon.
What did the court decide?
Application allowed: Mr. Justice Darshan Singh, former Judge of this Court (House No. 56, Sector 16-A, Chandigarh), appointed Sole Arbitrator, subject to compliance of statutory requirements including Section 12 of the 1996 Act; parties to first appear before the arbitrator on 20.05.2025 at 10.00 A.M.; arbitrator's fee payable per the Fourth Schedule of the 1996 Act; proceedings to be completed within the time limit under Section 29-A of the 1996 Act.