M/S Nkc Constructions Pvt. Ltd. v. the State of Punjab and Ors.
Case brief
What is this about?
The High Court issued mandamus directing the State to address pending representations regarding outstanding payment of Rs.80.84 lakhs for construction work. The Court directed payment with 6% interest if entitlement is established or a reasoned order if not. Petition disposed.
What did the court decide?
Direction to respondent No.5 to consider pending representations and pass order within two months; if entitled, pay amount with 6% interest.