Manohar Lal Jain v. HUDA & Ors.
Case brief
What is this about?
The petitioner challenged the cancellation of his provisional industrial plot allotment due to failure to deposit the required balance amount and non-compliance of other terms. The court upheld the cancellation as the petitioner did not meet the conditions within the stipulated time. However, it directed the refund of the deposited amount with interest based on Supreme Court precedent.
What did the court decide?
The order of cancellation was dismissed regarding legality; however, the petitioner was directed to receive a refund of the deposited amount along with interest at 10% per annum.