Compliance-closure oral order of Patna High Court dated 19-06-2026 in MJC No.147 of 2026 (arising from CWJC No.14435 of 2025, prior order dated 07.10.2025). Petitioner: Suresh Prasad Singh (Muzaffarpur, Bihar); Opposite Parties: State of Bihar through Principal Secretary, Building Construction Department (Sri Kumar Ravi), Sriniwash Singh (Superintending Engineer, Building Circle, Muzaffarpur), Satyendra Kumar Choudhary (Executive Engineer, Building Division, Muzaffarpur). Advocates: Raju Kumar for petitioner; Binita Singh (Standing Counsel 28) and Ujjawal Bhushan (AC to SC28) for opposite parties. Result: MJC closed/disposed; no statutory provisions or precedents cited.
What did the court decide?
The present MJC is closed, as nothing remains to be adjudicated following compliance of the order in CWJC No. 14435 of 2025 dated 07.10.2025.