M/S Aastha And Saumya Construction v. The State of Bihar
Case brief
What is this about?
Foreclosure of road agreement; Widening & Strengthening of Jariso chowk (SH-88) to Bharat Chowk (SH-56) Bypass road; RCD Road Division Benipur; Letter of Acceptance memo no. 77 dated 27.01.2023; land unavailable for work; extra work payment claims; soil work difference; additional levelling GSB; extra carriage via Munger; widening and DLC work; clause 10CC benefits; GST rate difference 12% to 18%; time extension deduction Rs.49,00,000; penal interest 18%; coercive action restraint; agreement no. 05 SBD/2022-23; representations dated 21.04.2025 and 23.03.2026 (Annexure P/10 series); direction to Additional Chief Secretary Road Construction Department Bihar; disposal at admission stage with consent; six-week timeline; opportunity of hearing; Patna High Court CWJC.
What did the court decide?
Direction to Respondent No. 2 (Additional Chief Secretary, Road Construction Department, Government of Bihar) to consider the petitioner's representations dated 21.04.2025 and 23.03.2026 (Annexure P/10 series) expeditiously, preferably within 6 weeks of receipt of a copy of the order; petitioner to be afforded an opportunity of hearing before any order; orders to be communicated to the petitioner; liberty to furnish a copy of the order with a fresh representation. All monetary and foreclosure prayers left undecided on merits.