What is this about?
Land acquisition - bridge-cum-road under Pradhan Mantri Gram Sadak Yojna over petitioner's land (Khata No. 185, Khesra No. 3384, 1 katha 12 dhurs, Mauza Khuguni (Patni), Thana No. 73, Ramgarhwa, East Champaran) - mandamus sought for acquisition and compensation at government rate (Rs. 4.48 lakhs claimed at Rs. 2.80 lakh/katha) and stoppage of construction till acquisition - writ petition disposed of with liberty to petitioner to approach Collector, East Champaran within four weeks; Collector to hear parties and pass reasoned order at earliest - Coram: Rajiv Roy, J.
What did the court decide?
Liberty to the petitioner to approach the Collector, East Champaran within four weeks; the Collector to take up the matter and, after hearing the parties, pass a reasoned order at the earliest. ¶¶24