Land acquisition compensation writ, Vaishali; Hajipur Sugauli Railway Line Project No. 9 of 2007-08; 70 decimals, Kheshra No. 2335, Khata No. 1754, Mouza Ghataro, P.S./Anchal Lalganj; Section 15 objection petitions under New Land Acquisition Act, 2013 (Annexures 5, 9, 12 series, 13); pending title suit T.S. No. 139 of 2006 before Sub-Judge IIInd, Vaishali at Hajipur; recovery of compensation with interest from respondent nos. 10, 11, 12, 15, 16, 29 (payments of 30.1.2013 and 7.3.2013, Annexure-8 series); peremptory notice dated 25.08.2025 to respondent nos. 04-29 rejected 22.09.2025 for non-compliance; file perused and consigned; writ disposed without adjudication; mandamus; Patna High Court; Rajiv Roy, J.; Devendra Singh v. State of Bihar.
What did the court decide?
On 25.08.2025, notice was issued to respondent nos. 04 to 29 in the writ petition and the order was peremptory.