T.N.B. College, v. The State of Bihar
Case brief
What is this about?
Keywords: Consumer Grievance Redressal Forum non-compliance; Ombudsman; Section 42(6) Electricity Act 2003; alternative remedy; writ disposal; coercive steps restraint; SBPDCL; electric supply dues; Bihar; T.N.B. College Bhagalpur. Single-judge oral order disposing CWJC 8216/2025 by routing the petitioner to the statutory Ombudsman remedy with an interim four-week anti-coercion direction; no merits adjudication, no precedent engagement.
What did the court decide?
Liberty granted to the petitioner to approach the Ombudsman under Section 42(6) of the Electricity Act, 2003 within four weeks; the authority to consider the representation/complaint and pass orders in accordance with law after notice to all parties; authorities restrained from taking coercive steps for four weeks only. ¶25