Sri Balajee Enterprises v. The State of Bihar
Case brief
What is this about?
CWJC No. 7159 of 2024, High Court of Judicature at Patna, decided 13-02-2025 (Ashutosh Kumar, ACJ; Partha Sarthy, J). Contractor Sri Balajee Enterprises, debarred after several extensions of time in a Building Construction Department (Government of Bihar) contract, sought a decision on post-facto extension of time by the Departmental Tender Evaluation Committee and denotification of the debarment; extension had been allowed retrospectively by the Superintending Engineer. Writ petition disposed of with the decision and denotification to be taken within eight weeks. Keywords: post-facto extension of time; debarment; denotification of debarment; Departmental Tender Evaluation Committee; Superintending Engineer; government contract; Building Construction Department Bihar; contractor debarment; time extension competence.
What did the court decide?
Writ petition disposed of with the expectation that the necessary decision regarding post-facto extension of time be taken by the Departmental Tender Evaluation Committee (the process being clearly delineated) and that a necessary denotification order of debarment be made, within a period of eight weeks; interlocutory application(s), if any, also disposed of accordingly