M/S Rehanam Construction Pvt. Ltd. v. The Chairman Cum Managing Director
Case brief
What is this about?
Contractor sought reimbursement of GST differential amount and royalty dues from Bihar Police Building Construction Corporation under SBD Clause 35. Court directed petitioner to submit complete claim with information sought by Superintending Engineer; Corporation to pass speaking order within two months and pay admitted claim within one month.
What did the court decide?
Liberty to submit complete GST claim within two months; Corporation to decide per SBD Clause 35 by speaking order within two months and pay admitted claim within one month.