Radhey Shyam Prasad v. The Union Of India and Ors.
Case brief
What is this about?
Land acquisition compensation writ (Siwan, Bihar) disposed with redirection to arbitration: petitioner Radhey Shyam Prasad sought enhanced compensation under Sections 26 and 27 RFCTLARR Act, 2013 [Act No. 30 of 2013] for land taken for NH-85 widening; NHAI objected that remedy lies under Section 3G(5) National Highway Act, 1956 [Act No. 48 of 1956]; court directed filing of application within 30 days with delay condoned and arbitrator to decide within three months. Keywords: enhanced compensation, RFCTLARR Act 2013, Section 3G(5), arbitrator, National Highway Act 1956, NH-85, Siwan, CWJC 3741/2019.
What did the court decide?
Writ petition disposed of; petitioner directed to file an application (within 30 days, delay condoned) before the arbitrator under Section 3G(5) of the National Highway Act, 1956, raising enhancement of compensation per Sections 26 and 27 of the RFCTLARR Act, 2013; arbitrator to pass final order within three months of completion of appearances.