M/s P. K. Construction Pvt. Ltd. v. The State Of Bihar and Ors.
Case brief
What is this about?
Patna High Court CWJC No.20356 of 2018 (filed 2018; disposed 18-08-2025), single judge Smt. G. Anupama Chakravarthy (oral order). M/s P. K. Construction Pvt. Ltd. v. State of Bihar (Road Construction Deptt.) and Bihar State Road Development Corporation Ltd. officers (MD, DMD Technical, SDO, Executive Engineer, Assistant Engineer, Junior Engineer - PIU Digha). Advocates: Shyam Kishore for petitioner; Sushil Kumar (Gp22) and KK Singh (AC to GP22) for respondents. Disposition: writ petition dismissed as infructuous after petitioner's counsel reported the grievance stood redressed and nothing remained for adjudication. No statutes, precedents, issues, or monetary amounts recorded; no relief granted.
What did the court decide?
Because learned counsel for the petitioner reported that the petitioner's grievance had been redressed and nothing remained for adjudication, this Court dismissed the writ petition as infructuous.