Dilip Kumar v. The Union Of India and Ors.
Case brief
What is this about?
NH-30 / National Highway 30 land acquisition compensation writ, Patna High Court, disposed of 01-07-2025; mandamus for compensation with upto date interest and 60% soletium (solatium); Plot No. 693, Khata no. 124, Thana no. 39, Mouza Abdul Rahmanpur, Patna Sadar; comparable payments to holders of Plot nos. 689 and 699; Learned Arbitrator Patna order dated 09-04-2013 in L.A. case no. 01/2012-13; petitioner directed to Arbitrator-cum-Commissioner, Patna Division within four weeks; matter to conclude in six months after hearing all parties; Court declined to decide as no private person impleaded as respondent; single-judge bench (Rajiv Roy, J).
What did the court decide?
Liberty to the petitioner to approach the Arbitrator-cum-Commissioner, Patna Division, Patna within four weeks alongwith all relevant documents; the Arbitrator-cum-Commissioner to conclude the matter within six months after hearing all parties.