Ashok Mistri v. The Bihar State Power Holding Company Limited
Case brief
What is this about?
Patna HC CWJC 19375/2024, Justice A. Abhishek Reddy, 17-01-2025 — writ petition for electricity connections DISPOSED: Respondent Nos. 6 & 7 (Asst. Electrical Engineers, SBPDCL sub-divisions Digha & Ashiyana) directed to accept applicants' connection applications with requisite amounts and decide per law within 4 weeks. Invoked (referred, not adjudicated): SC Civil Appeal No. 7572/2011 Sri Chandu Khamaru v. Smt. Nayan Malik; s. 43 Indian Electricity Supply Act, 2003; Cl. 4.13(B) Bihar Electricity Supply Code, 2007. Counter affidavit on record; no dissent; no amounts.
What did the court decide?
Direction to Respondent Nos. 6 and 7 (Assistant Electrical Engineers, SBPDCL Electric Supply sub-Divisions, Digha and Ashiyana) to accept the petitioners' electrical-connection applications with the requisite amounts, consider them strictly in accordance with law, and complete consideration within four weeks of receipt of the order copy.