Vibha Singh v. The Bihar State Power Holding Company Limited
Case brief
What is this about?
Electricity connection mandamus; SBPDCL Digha and Ashiyana sub-divisions directed to accept application with requisite deposit and consider per law within four weeks; Section 43 Indian Electricity Supply Act, 2003; Clause-4.13(B) Bihar Electricity Supply Code, 2007; Sri Chandu Khamaru Vs. Smt. Nayan Malik, Civil Appeal No. 7572/2011; writ disposed with directions; Patna High Court, CWJC No. 1719 of 2025, decided 05-02-2025, single judge A. Abhishek Reddy.
What did the court decide?
Direction to Respondent Nos. 6 and 7 (Assistant Electrical Engineers, SBPDCL, Digha and Ashiyana sub-divisions) to accept the petitioners' application for electrical connection along with the requisite amount and consider it strictly in accordance with law, within four weeks of receipt of the copy of the order. ¶42