Patna HC CWJC No.5386 of 2024 (decided 21-11-2024, Nawneet Kumar Pandey, J) - sand ghat mining Bhojpur; joint pre-excavation survey ordered by Environment & Forest experts in presence of both parties; petitioner highest bidder Sand Ghat No. 20 (19 hectars); LOI no. 4723 dt 25.11.2022; Rule 29 / Rule 29(A) / Rule 66 Mining Rules 2019; SC guidelines order dt 10.11.2021 in CA 3661-3662 of 2020, fresh DSR; third-party excavation till September 2023; pits beyond 3-metre permissible depth; penalty/apprehension; letter no. 277 dt 15.01.2024 fluvial replenishment; writ petition disposed, exercise within one month.
What did the court decide?
Direction that a survey of the allotted sand ghat be conducted by expert persons of the Department of Environment and Forest in the presence of representatives of both the parties before excavation begins, with the entire exercise to be completed within one month.