Arjun Singh v. The State of Bihar
Case brief
What is this about?
Land acquisition compensation non-payment; 6-lane Ganga River Green Field Bridge Project; plots Khata No. 591 Plot Nos. 1629, 1639, 2706 village Dilawarpur Gobardhan, Vaishali; District Land Acquisition Officer Vaishali Hajipur; National Highway Authority of India Muzaffarpur; representation with documents; verification and payment within 12 weeks; CWJC No. 4396 of 2024; Patna High Court; Justice A. Abhishek Reddy; disposed 02-12-2024.
What did the court decide?
Writ petition disposed of with directions: petitioners to submit a representation with all necessary documents within four weeks to Respondent No. 4; the District Land Acquisition Officer, Vaishali, Hajipur, to verify the documents and pay the compensation for the remaining plot, completing the entire exercise expeditiously and preferably within 12 weeks of receipt of the representation.